03 - Visualization how-to
How to use Gantt
Use this guide to operate the Gantt viewer, including schedule selection, grouping, filters, path tools, display settings, and exports.
Quick Start
- Open a project workspace and choose Gantt from the project-level module buttons.
- Select the schedule and optional baseline schedule.
- Use Group By, Collapse To, Search Activities, and Filter to shape the activity list.
- Use the timeline controls to zoom, fit, scroll, and inspect activities.
- Use Print, Export, or Export Schedule from the bottom action bar when you are ready to share or download.
01
Open the Gantt viewer
- Go to a project workspace.
- Choose Gantt in the Project level modules section.
- Use Open Gantt to launch it in the embedded workspace.
- Use the expand control to review the Gantt in full-screen workspace mode.
- Use Open in new tab if you want the Gantt separate from the project page.
02
Load and switch schedules
- Use the main schedule selector to choose the current schedule.
- Use the baseline selector to choose the comparison schedule when baseline bars are needed.
- If using the standalone viewer, drop a XER schedule into the drop zone or use Select .xer file.
- Use Select baseline .xer when the standalone viewer needs a separate baseline file.
- Use Reset Filters to clear filters without changing the loaded schedule.
04
Use WBS grouping and row controls
- Use Group By to choose WBS Code or another available grouping.
- Use Collapse To to choose the default WBS depth shown on screen.
- Click WBS headers to expand or collapse individual sections.
- Use row selection circles or activity rows to select a specific activity.
- Use the left activity table and right timeline together; scrolling keeps the rows aligned.
- Use the column divider or available column controls to adjust the activity table when text needs more space.
05
Search and filter activities
- Type into Search Activities to filter rows by activity ID or name.
- Click Filter to open filter controls.
- Use float filters such as Any Float, 0d, 5d, 10d, or 20d where available.
- Use activity-code filters by selecting a code type and then a value.
- Use scope controls such as Full Schedule or All Activities to return to a wider activity set.
- Remove active filter chips to clear individual filters.
06
Use activity details and path tools
- Click an activity row or bar to select it.
- Use Show Popups to enable or disable hover/detail popups.
- Use Calculate Critical Path to This Activity when you want the viewer to trace to the selected activity.
- Use Show Driving Predecessors to highlight predecessor logic for the selected activity.
- Use Show Driving Successors to highlight successor logic for the selected activity.
- Use Clear Highlighted Path to remove the path highlight.
- Use the Logic toggle to show or hide relationship lines when available.
07
Adjust display and colors
- Use Show Metrics to show or hide the metrics cards above the Gantt.
- Use Columns to choose which left-table fields are visible.
- Use WBS Colors or WBS Level Colors to change WBS row coloring.
- Use Bar Colors or Bar & Milestone Colors to change activity and milestone colors.
- Use Show Planned to show or hide planned/baseline-style bars where available.
- Use Health Panel, Legend, or Health Flags from the options area when you need those panels visible.
08
Use actions and exports
- Use Print to open the printable Gantt output.
- Use Export to download the current Gantt view data or visual export available in the module.
- Use Export Schedule to download the schedule output when that option is enabled.
- Use Reset Scenario when what-if or scenario edits are active.
- Use Reset Filters before exporting if you want the full activity set included.